The Actual News

Stay informed without the news wearing you out.

Plan for multibillion-pound Sizewell nuclear plant a ‘terrible deal’ for UK taxpayers, MPs say

Plan for multibillion-pound Sizewell nuclear plant a ‘terrible deal’ for UK taxpayers, MPs say

Summary

A parliamentary watchdog warned that Sizewell C could cost up to £47.7bn and expose UK taxpayers and energy customers to major financial risks. The government says the project is progressing and could save £2bn a year across the energy system once it operates.

Key Facts

  • The Public Accounts Committee said construction overruns could require an extra £9.8bn before 2040, with a further £12bn in costs over the plant’s 60-year operating life.
  • The government owns 44.9% of Sizewell C, EDF holds 12.5%, Centrica 15%, La Caisse 20%, and Amber Infrastructure 7.6%.
  • The government took a larger stake after buying out Chinese state nuclear developer CGN, citing national security concerns.
  • The watchdog said public funds and energy customers could bear multibillion-pound overruns, while private investors would need to contribute only £30m more.
  • The project is projected to cost between £40.5bn and £47.7bn, with construction due to finish between 2039 and 2043.
  • The committee asked the government to provide its cost scenario analysis within three months and report on development every six months.
  • The government said investors have incentives to complete construction cheaply and quickly, and that more than 2,000 workers are already on site.
Read the Full Article

This is a fact-based summary from The Actual News. Click below to read the complete story directly from the original source.

Monday's biggest stories, one calm email.