Trump's biggest project is running out of time

Trump's biggest project is running out of time

Summary

About 619 miles of primary border wall remained to be built as of November 10, according to Customs and Border Protection data. At the recent construction pace, the wall would not be finished until late 2029, after President Donald Trump is scheduled to leave office in January 2029.

Key Facts

  • Construction averaged 3.9 miles a week from mid-June to early November, up from 2.6 miles a week earlier in the year.
  • Much of the remaining wall is planned for Texas, including West Texas and the Big Bend region.
  • More than half a dozen lawsuits in West Texas challenge border-wall construction.
  • The federal government may need to pursue individual eminent domain cases to obtain private land for construction.
  • Texas Land Commissioner-elect Benjamin Flores opposes wall plans in West Texas and has proposed considering surveillance technology instead.
  • Texas owns 31 linear miles of land along the border, and its General Land Office sent Customs and Border Protection and a contractor a cease-and-desist letter over unauthorized construction in July.
  • Homeland Security Secretary Markwayne Mullin has said he was planning for a physical wall from the Pacific to the Gulf of America by the following year; Customs and Border Protection Commissioner Rodney Scott set a deadline of the end of 2027.
Read the Full Article

This is a fact-based summary from The Actual News. Click below to read the complete story directly from the original source.