World Bank official says Lebanon reconstruction making slow progress
Summary
Lebanon has used only a small share of World Bank reconstruction aid approved after the 2024 war. The bank cites slow progress amid delays in loan approval, continued fighting and a worsening security situation in the south.Key Facts
- The World Bank approved $250 million in June 2025 to clear rubble and repair damaged public infrastructure in Lebanon.
- A September progress report showed that only $4.2 million had been paid out, compared with a projected $100 million by July 2026.
- The World Bank estimated that reconstruction after the 2024 war would cost about $11 billion.
- Prime Minister Nawaf Salam’s office said parliamentary approval delays and worsening security had held up project work.
- The United Nations estimates that at least 304,500 people remain displaced inside Lebanon, down from 1.2 million.
- The article states that up to 4,500 people have been killed in Israeli attacks.
- The World Bank projected Lebanon’s economy would shrink by 6.4 percent in 2026.
This is a fact-based summary from The Actual News. Click below to read the complete story directly from the original source.