NextDC vows to keep future datacentres away from homes after community backlash in Melbourne
Summary
NextDC says it will avoid future datacentre developments near homes after community opposition delayed an expansion at its M3 site in West Footscray, Melbourne. Chief executive Craig Scroggie said the company would involve residents earlier and improve how it handles community concerns.Key Facts
- Community protests led power provider Jemena to pause work on 22-metre power poles for the M3 expansion.
- The expansion delay followed a reported 40% drop in NextDC’s share price; the price later recovered to more than $9 a share.
- NextDC plans to establish a community consultative committee and a standing forum for residents and local stakeholders.
- The company plans to create a dedicated project website and contact channels with set response times for inquiries and complaints.
- NextDC chair Doug Flynn said the company does not intend to pursue new developments near residential properties.
- Shareholders issued a second strike against executive pay at the annual general meeting, but defeated a motion to spill the board.
- Flynn said an employee overseeing community engagement at Jemena had left the business after the dispute.
This is a fact-based summary from The Actual News. Click below to read the complete story directly from the original source.