Summary
New South Wales passed legislation allowing the Mount Pleasant coal mine in the Hunter Valley to raise annual production by 32%, from 12.5 million tonnes to 16.5 million tonnes, until 2032. The law follows a High Court ruling that invalidated approval for a larger expansion and drew criticism from climate groups and opposition politicians, while the government and Coalition said it would protect jobs.Key Facts
- The New South Wales government and the Coalition voted to pass the Mount Pleasant mine legislation.
- The law allows annual production to rise from 12.5 million tonnes to 16.5 million tonnes until 2032.
- The High Court ruled that approval for an expansion to 21 million tonnes a year by 2048 was invalid.
- The court found that the Independent Planning Commission had not properly considered conditions to limit emissions from burning the coal overseas.
- Premier Chris Minns said the legislation would save 400 jobs.
- The Greens and Animal Justice Party opposed the legislation, and the Greens sought almost 200 amendments.
- The Coalition said hundreds of mine workers could lose their jobs without the legislation.
- The Hunter region is expected to be a key battleground in the March 2027 New South Wales state election.