Summary
Three large housing developments in England promised a combined 7,400 homes, but only 326 have been built so far. The Middlesbrough and York projects show how funding, infrastructure planning and developers’ financial incentives can slow large housing schemes.Key Facts
- Middlesbrough announced plans for 2,400 homes at Middlehaven in 2004, but 216 homes have been built there.
- Middlesbrough Council said the original £500 million figure was an estimate of the development’s total cost, not secured funding.
- The 2008 financial crash led to the departure of Middlehaven’s development partner, according to the council.
- Middlesbrough Council announced plans in September for 462 homes on the site, as an initial step toward a larger plan for 3,400 homes.
- York announced a plan for 3,000 homes in 2001, but no homes had been built there by 2026.
- The three developments in Middlesbrough, York and the Isle of Sheppey promised 7,400 homes in total; 326 have been built.
- The Labour government has a target to build 1.5 million homes in England by the next election, which is likely to be missed.