Flagship UK gigafactory plan in turmoil after it loses second builder in five months

Flagship UK gigafactory plan in turmoil after it loses second builder in five months

Summary

Agratas’ £5.2bn electric-vehicle battery factory in Somerset faces further delays after contractor TSL decided to leave following disagreements over cost and schedule. The project, which has received a £380m pledge of UK government support, has a January 2028 target, but Agratas says it remains on track to meet customer requirements.

Key Facts

  • Agratas is building the Somerset factory to supply batteries to Jaguar Land Rover, with both companies part of Tata Group.
  • TSL is the second main contractor to leave the project in five months; Sir Robert McAlpine was dismissed in June.
  • TSL is expected to leave the site within two or three months, and no replacement main contractor has been selected.
  • NG Bailey, which handles mechanical, electrical and plumbing work at the site, could be considered to take over the full build.
  • Tata initially planned to start production in 2026, then moved the target to 2027; the factory’s latest target is January 2028.
  • The UK government has pledged £380m toward the £5.2bn project, although not all of the support has been paid.
  • JLR has secured batteries from other suppliers, so its electric-vehicle sales plans are not expected to be affected; its initial vehicles will not use British-made batteries.
  • Agratas workers have faced a planned move from Coventry to Somerset, and some may choose redundancy rather than relocate.