How Israel is fast-tracking data centres in bid to become ‘AI superpower’
Summary
Israel is accelerating data-centre development as part of a plan to expand its role in artificial intelligence. The effort includes a $1.5 billion facility planned near Ashdod, but electricity-grid limits could slow construction and expansion.Key Facts
- Prime Minister Benjamin Netanyahu said his government aims to make Israel a global AI superpower and said the country could become the third AI power within five years.
- Israel has 67 data centres, according to Data Center Map.
- The planned Ofek Data Center near Ashdod is expected to open in the second half of 2029.
- Ofek is expected to begin with 130 megawatts of capacity and later expand to 200 megawatts.
- The project is expected to cost $1.5 billion initially, with another $5 billion planned for future upgrades.
- The Israeli Electrical Authority capped the capacity of new data centres at 200 megawatts amid high demand for grid connections.
- Nvidia has 6,000 employees across seven research and development centres in Israel, and plans a campus near Haifa that could accommodate up to 10,000 employees.
- Nvidia's networking business generated more than $21 billion in revenue in the third quarter of 2026, about 18 percent of its total quarterly revenue.