Google has paused construction of an AI data centre in Farciennes, Belgium, pending further guidance. Belgian officials say the work lacked required planning permission, and a court hearing is scheduled for the new year.Key Facts
- Google said it paused construction in Farciennes pending additional guidance.
- Wallonia government spokesperson Nicolas Yernaux said the project lacked the correct planning permission and called the violation a major offence.
- Google said it remains committed to complying with local laws.
- Google sought to amend its planning permission to replace air cooling with a system that would draw water from the nearby River Sambre.
- Regional officials rejected the proposed change, but construction continued, raising concerns among nearby residents and environmental groups.
- A court hearing on the case is scheduled for the new year.